Construction Underway at Pin Oak Lodge
posted on 2/28/24 · posted by Conservation
Pin Oak Lodge construction has started. The concrete slab has been prepared and the safe room constructed on the south east corner. By the time you are reading this, the sidewalls and trusses will be up. The building shell is scheduled to be finished by the end of February. The next few months the electrical, mechanical, plumbing and interior will be installed. Completion of the project is set for July 1, 2024. Pin Oak Lodge will remain closed until we get moved in and all set up. Thank you for everyone’s continued support.